A year on from Storm Ciara, a £10 million package of work to repair flood embankments on the Lower River Aire is making progress.
A total of 18 defences have been repaired to protect local communities from the risk of flooding, seven projects are currently underway with another nine set to start in the coming months.
February 2020 was the wettest on record for Yorkshire, which resulted in large amounts of water spilling over from the River Aire and flooding the washlands, filling them to capacity and in some cases even overflowing.
This then damaged a number of flood embankments which sit alongside the river to protect local communities. Temporary emergency repairs were then carried out in the immediate aftermath of the flooding and the Environment Agency has spent the rest of the year making permanent repairs at various locations across the Lower Aire washlands.
More repair work begun on Monday 1st March at Heck Ings and repairs have also begun at Temple Hirst on an embankment net to the Sloop Inn pub.
Timetable of repairs and works completed:
- At Heck Ings, repairs have started on the riverside embankment which was damaged in the floods because of wave action and flood water overtopping the bank. The Heck Ings flood storage reservoir is part of a series of reservoirs that help protect Gowdall and the surrounding villages from flooding from the River Aire.
- Work at two sites at Hirst Courtney has started with repairs to flood embankments in the village and work to prevent river channel erosion near the Sloop Inn pub at Temple Hirst. Rock armour is being used to strengthen the embankment.
- Work is underway to build up a low spot in an embankment at Brotherton Ings and repairs have started to an embankment at Eskamhorn Farm, Rawcliffe.
- A new flood defence wall is being proposed at Newlands, with work due to start shortly. Temporary repairs are in place until permanent works can start.
- Works to repair embankments at Hensall are due to start in March.
- Work to repair the embankment at Chapel Haddlesey is also due to start in March.
- Repair work has been completed at Little Airmyn, West Holme, and West Haddlesey.
- Repairs at Poor bank and Pickhill embankments are complete, which are part of reservoirs that help reduce the flood risk to the communities of Gowdall and Snaith.
Kimberley MacPherson, West Yorkshire Operations Manager at the Environment Agency, said: “The floods of Storm Ciara had a devastating impact on communities in Yorkshire. Our thoughts remain with those affected, especially people who are yet to return to their homes and who have also had to cope with the impact of the coronavirus pandemic.
“Our £10 million package of repairs is progressing well. These refurbished flood defences were recently put to the test again during Storm Christoph in January and successfully withstood the winter flood conditions. We’ll continue to work at pace with the aim of completing our repair programme by the end of the summer.”
If you would like to read more stories like this, then please click here
Related Articles
Related Articles
- Construction Reforms Must Be Accelerated
5 Nov 21
Government and industry must work together to spur an improvement in construction buying habits if
- Sky is the Limit for Createmaster
3 Nov 21
Createmaster has won the contract to provide all handover information for Sky Studios Elstree, in
- On-Site Sustainability & Innovation Hub Revealed
2 Nov 21
Following on from the launch of the on-site Training Centre at Mercia Park, Winvic Construction