Sector - Public Sector
York flooding scheme requires less road closures
22 Jan 20

Following the infamous Boxing Day Floods of 2015, the government promised the provision of £45M to the city of York to help protect itself against any such flooding taking place again, with recent investigations revealing that intrusion caused by the works will be less than first anticipated.
Initial plans for the York flooding protection scheme detailed the construction of an eight metre deep wall of concrete piles under Terry Avenue, to prevent water ingress during flooding, with such a process then requiring the closure of Terry Avenue for a period of 18 months.
However, now that the Environment Agency, who are undertaking the project, are considering a more modern method of construction known as grout injection, the necessary closure period of Terry Avenue has reduced drastically to just 12 months as opposed to 18.
As a result of the newly proposed grout injection technique, large scale excavation will need to take place along the bank of the River Ouse for preparatory works, resulting in the necessary acquisition of planning permission as well.
The Environment Agency Project Director, Ben Hughes said: “It is great news that a new less invasive solution, and one that takes six months less time, has been found. This will cause significantly less disruption to people than would otherwise have been the case.
“During our investigations in October a number of incidents arose where work had to stop and members of the public needed to be escorted through the active working area.
“This caused significant delay to even these minor works and to ensure Terry Avenue was fully reopened on time we had to impose a 24 hour road closure for vehicles.
“Unfortunately, these issues are out of our control and we can only conclude that it is not viable to safely accommodate the public in these areas during the main works.”
If you would like to read more articles like this then please click here.
More Public Sector News
- Flagship Ulster University capital build project procurement opportunity now live
9 Oct 25
Submit a tender now.
- Nuclear security boost
1 Oct 25
The UK and US have signed a new agreement designed to accelerate nuclear power projects.
- RAAC removal progress
26 Sep 25
The government has announced significant progress in its RAAC programme.
-
Sector Press Releases
- UKIS 2018 : Keynote speakers announced
UKIS 2018 has announced the keynote speakers for this year’s event.
- Transforming infrastructure
The government has released new plans aimed at revolutionising British infrastructure and boosting the construction sector’s productivity.
- Record infrastructure investment
National Infrastructure and Construction Pipeline has been published, which confirms over £600Bn of investment in UK infrastructure.
- The UK’s Leading Infrastructure & Supply Event
Connect with major infrastructure projects at the UK Infrastructure Show
- Infrastructure and Projects authority confirms presence at UKIS
BiP Solutions are pleased to announce a new partner for the UKIS event, the Infrastructure Projects Authority.
- Confidence suffers as activity stalls
The Vinden Partnership reacts to October's figures.
-
Sector Case Studies
- The Importance of Good Architectural Design
Our mental health is heavily influenced by the walls we spend our time within.
- Director – Trouble Ahead? What Are Your Options?
Running a company involved in the construction sector is hard work.
- Civic Centre – Ipswich
Over 15,000 tonnes of concrete were removed from site.
- Cargill project to renew exhausts of industrial fryers
Cargill commissioned ASAP Fire and Bryland Fire to design, supply and install a new system.
- Tennison Road Bridge
The brief was to demolish sections of the bridge over a series of weekend possessions.
- Bridge 404 – Felixstowe to Nuneaton Loop