The Environment Agency has officially completed the third stage of its works on the Great Ouse Catchment Project which seeks to raise the height of the flooding embankment to protect more than 2,000 properties and over 67,000 hectares of agricultural land.
The Great Ouse Catchment Project, which was initially taken on by the Environment Agency in 2017, involves the heightening of the Middle Level Barrier Bank (MLBB) and part of the South Level Barrier Bank (SLBB) over the course of a four year period.
In terms of the work that is being carried out, construction can only take place during the summer months, meaning that works have and can only take place in the summers of 2017, 2018, 2019, and 2020, with a further year needing to be allowed for the growth of new grass and foliage in the summer of 2021.
Prolonged periods of wet weather, the evolving design of the new embankments, and the material inconsistencies which have resulted from it, have also resulted in a change to the intended profile of the embankment as well as extensions to the intended construction period.
The Environment Agency Operations Manager for the Great Ouse Catchment Project, Claire Jouvray stated: “We have had a really challenging year this year with road works impacting deliveries and the wet weather in September and October stopping work on the bank.
“Thanks to partners, our contractors, neighbours and local authorities we have been able to keep disruption to a minimum.
“We would like to thank the local community for their patience and understanding during this complex programme of work which will take longer than predicted at the outset.
“We will be holding public drop in events in the new year to showcase the work we have done so far, to outline the revised timescale for this vital scheme and discuss our plans for the Welney Wash road temporary barrier.”
If you would like to read more articles like this then please click here.
More Public Sector News
- Leeds Beckett University collaboration to drive innovation in construction industry
25 Apr 24
Leeds Beckett University have partnered YORhub drive innovation in the construction sector
- Balfour Beatty awarded contract to build Scotland’s first net zero prison
24 Apr 24
Balfour Beatty has confirmed that it has been awarded a contract to construct the new
- Planning application submitted for major new government hub in Darlington
11 Apr 24
The Government Property Agency (GPA) has submitted a planning application to Darlington Borough Council to
-
Sector Press Releases
- UKIS 2018 : Keynote speakers announced
UKIS 2018 has announced the keynote speakers for this year’s event.
- Transforming infrastructure
The government has released new plans aimed at revolutionising British infrastructure and boosting the construction sector’s productivity.
- Record infrastructure investment
National Infrastructure and Construction Pipeline has been published, which confirms over £600Bn of investment in UK infrastructure.
- The UK’s Leading Infrastructure & Supply Event
Connect with major infrastructure projects at the UK Infrastructure Show
- Infrastructure and Projects authority confirms presence at UKIS
BiP Solutions are pleased to announce a new partner for the UKIS event, the Infrastructure Projects Authority.
- Confidence suffers as activity stalls
The Vinden Partnership reacts to October's figures.
-
Sector Case Studies
- The Importance of Good Architectural Design
Our mental health is heavily influenced by the walls we spend our time within.
- Director – Trouble Ahead? What Are Your Options?
Running a company involved in the construction sector is hard work.
- Civic Centre – Ipswich
Over 15,000 tonnes of concrete were removed from site.
- Cargill project to renew exhausts of industrial fryers
Cargill commissioned ASAP Fire and Bryland Fire to design, supply and install a new system.
- Tennison Road Bridge
The brief was to demolish sections of the bridge over a series of weekend possessions.
- Bridge 404 – Felixstowe to Nuneaton Loop
A three-span steel bridge had to be replaced over the River Gipping.