Time reduced on viaduct improvements
22 Jul 19

Highways England have utilised new and innovative technologies to complete imperative renewal work on the Hill House viaduct in Suffolk, a task normally requiring three months, within just four weeks.
By applying the new technique of hydro-demolition and applying new materials such as the new rapid drying concrete to the £1.2M project on the A14 route over the River Gripping, Highways England were able to achieve the project over the course of two weeks and two additional weekends.
Hydro-demolition, or hydro-blasting, is a removal technique through which deteriorated and sound concrete is removed through the use of high-pressured water whereas the rapid drying concrete is exactly as described, with 19 tonnes of the material taking just four hours to dry whereas traditional concrete would take up to seven days.
The Assistant Service Delivery Manager at Highways England, Ashley Prigmore stated: “Of the thousands of drivers that cross the Hill House viaduct daily, I’m sure most of them don’t give much thought to the joints supporting their crossing. They’re vital components and are designed to be replaced from time to time.
“We understand how important the A14 is to local people as well as business at home and abroad. By hydro-blasting and using a rapid drying concrete we were able to take a vital road upgrade that may have taken up to 12 weeks and completed them over the course of four weekends. This not only drastically minimised disruption to drivers, but meant the road remained open at peak times.”
Approximately 60 people were onsite every weekend throughout the project as a means of ensuring that the key components which required replacement on the bridge were safely delivered on time so that the A14 was able to be driveable ahead of the following morning.
Councillor Gary Green of Suffolk County Council added: “I would like to record my thanks for Highways England working closely with the local councils to ensure that the disruption to the residents of Stowmarket was kept to the minimum.”
The project was funded through part of a £55.8M investment fund for the improvement and maintenance of trunk roads and motorways in the East of England.
If you would like to read more articles like this then please click here.
More Public Sector News
- Flagship Ulster University capital build project procurement opportunity now live
9 Oct 25
Submit a tender now.
- Nuclear security boost
1 Oct 25
The UK and US have signed a new agreement designed to accelerate nuclear power projects.
- RAAC removal progress
26 Sep 25
The government has announced significant progress in its RAAC programme.
-
Sector Press Releases
- UKIS 2018 : Keynote speakers announced
UKIS 2018 has announced the keynote speakers for this year’s event.
- Transforming infrastructure
The government has released new plans aimed at revolutionising British infrastructure and boosting the construction sector’s productivity.
- Record infrastructure investment
National Infrastructure and Construction Pipeline has been published, which confirms over £600Bn of investment in UK infrastructure.
- The UK’s Leading Infrastructure & Supply Event
Connect with major infrastructure projects at the UK Infrastructure Show
- Infrastructure and Projects authority confirms presence at UKIS
BiP Solutions are pleased to announce a new partner for the UKIS event, the Infrastructure Projects Authority.
- Confidence suffers as activity stalls
The Vinden Partnership reacts to October's figures.
-
Sector Case Studies
- The Importance of Good Architectural Design
Our mental health is heavily influenced by the walls we spend our time within.
- Director – Trouble Ahead? What Are Your Options?
Running a company involved in the construction sector is hard work.
- Civic Centre – Ipswich
Over 15,000 tonnes of concrete were removed from site.
- Cargill project to renew exhausts of industrial fryers
Cargill commissioned ASAP Fire and Bryland Fire to design, supply and install a new system.
- Tennison Road Bridge
The brief was to demolish sections of the bridge over a series of weekend possessions.
- Bridge 404 – Felixstowe to Nuneaton Loop
A three-span steel bridge had to be replaced over the River Gipping.